University research / execution architecture / planning baseline

Rotating detonation engine Project atlas

One demonstrator. Six parallel workstreams. Evidence before release.
Stationary, instrumented research hardware; establish repeatable rotating-detonation operation.

GIVEN Physical research demonstrator ~28 weeks: optimistic, challenged / not a forecast Out of scope: flight / long duration / efficiency optimisation
FACT / given scope & rules ASSUMPTION / draft content & timing DECISION / hollow + dashed Not yet validated Validated (none recorded) Controlling chain / linked selection Failure & recovery

Cross-links: select a part, task, gate, recovery loop or evidence stage.

Layers
ASSUMPTION

Click a task, gate or recovery card for details. Select a hollow decision to trace what it unlocks. Keyboard: Tab to items; Enter/Space opens; arrow keys move between tasks; Escape closes details. Scroll horizontally on smaller screens.

01 / Parallel, not premature

CAD, controls, data tools and facility work start early. Use shared interfaces + provisional load ranges; release reviewed packages in stages.

02 / Release is conditional

CFD does not certify hardware safety. Pressure-containing and combustion-critical fabrication stays behind G2 reviews.

03 / Recovery is controlled

A failure changes the baseline, not the evidence standard. Re-enter a named gate; re-review and re-authorise where affected.

Accessible task register / all draft owners, inputs, deliverables, dependencies and acceptance criteria

All task-level execution criteria and detailed timing are ASSUMPTIONS for institutional review. No task or validation is represented as completed.

Task / owner / windowInputsDeliverableDependencyAcceptance (draft)